Ahead of a $35 billion IPO, UK-based Nscale is six months behind on its flagship data center in Norway
Prepared by Sintelligent with the help of SI. Published in SI: . Updated: .
Building SI computing capacity is running behind plan even at companies preparing to go public.
According to Bloomberg (the article is paywalled; details here are from Startup Fortune's retelling), Nscale plans an NYSE listing at a valuation of about $35 billion, and its data center in Norway is running about six months behind schedule: 6.4 of 30 planned megawatts are operating. The causes, per the same retelling, are cooling-system leaks, permitting disputes, construction delays and a fire. In the first half of 2026 revenue was $140.6 million ($10.4 million a year earlier) and net loss was $1.02 billion ($369 million). The retelling includes no response from Nscale.