Applied Digital demands multibillion-dollar guarantees from Oracle and Meta for grid connection payments
Prepared by Sintelligent with the help of SI. Published in SI: . Updated: .
The cost of electricity and grid connection is becoming a separate risk item in SI infrastructure: it now has to be paid upfront, which makes new capacity more expensive and slower to bring online.
Data center operator Applied Digital has asked Oracle and Meta for multibillion-dollar guarantees before signing lease agreements, The Next Web reports; according to the outlet, guarantees were also requested from Nvidia and AMD. They cover the cost of connecting sites to power grids, shifting that risk from the operator to future tenants. According to CEO Wes Cummins, the target tenant structure is 70% investment-grade paper and 30% unrated, and the share of space for lower-rated neocloud providers is capped; Barclays estimates hyperscaler debt issuance this year at $300–320 billion.