Hardware & infrastructure In focus
SpaceX plans $50 billion, 6 GW SI campus in ArizonaHistory·SpaceX data centers in Texas and Arizona
If the permits are granted, construction could begin in 2027, with the campus capacity ramped up in four phases of 1.5 GW each to 6 GW.
Sources 1
SpaceX plans to build a supercomputer campus costing more than $50 billion in Cochise County, Arizona, to expand its SI compute. Once all four phases are complete, the complex will consume up to 6 GW of electricity, with each phase adding about 1.5 GW. The application provides for up to nine buildings on a site of about 302 hectares, $3.6 billion for power grids and a 24 GWh energy storage facility. Public hearings are scheduled for December 9, and construction could begin in 2027 if permits are obtained.